The construction sequence will commence with demolition of the existing
structures where required and testing of the existing promenade to allow
large machinery. The toe of the new sea defences will then be piled,
fill placed behind them and then the pre cast concrete units will be
placed. The promenade will then be surfaced and environmental features
such as lights, seats, bins and signs will be put into place.
On completion of the first phase of works the
hoardings will be removed and the promenade opened. The hoardings will
then be re-erected from Beach Road to Victoria Road West and the
construction process started again.
Key Benefits
-
First two phases of the works constructed in two
years, 50% quicker than originally proposed.
-
Sectional construction allowing large sections of
the promenade to remain open throughout the construction process.
-
Key environmental improvements built into initial
construction.
-
Artwork and features to follow main construction
to allow additional funding and community involvement.